Moving Along

Masons are doing prep work. The chimney is all prepped so they are now moving on to other areas like the loggia. Stone will arrive in about a week and a half or so.
Framers are still at it doing pick up work. They did make this set of stairs much more stable today.

Fire sprinkler heads are being installed. There are more of them than I anticipated but I assume they are to spec. Electrician was also here today and getting his part well under way. Concrete forms are set for the ramp up to the front porch. Things are moving along.