Viktor finished sealing the stone today. That should complete his work. F&C had a guy here working at finishing the cabinet trim. They still need to put appliance panels on too. We got handles for the refrigerator so they can be put on with the panels. They were ordered in
McMinnville but Diana picked them up in
Tigard or we would have waited on them until the end of the week. The electrical final was passed yesterday and the plumbing final was passed today. Railing glass is still due to be installed on Thursday and then they can be signed off. Josh says he's trying to get occupancy on Friday. There is still a lot of cleaning and finishing up to do which is scheduled for next week. If all of that happens as planned, we may be able to actually move in a week from this Saturday. So, we are getting very close.